Tailor
made for our site - and
arriving in style along the new
southern entrance!
The
steel tube diet to keep
matters busy
The first pile for Cloud 8 is prepared
for driving
The
first pile marked and ready to go
The
rig is radio controlled by Steve
(right). Another 4 meter steel section
is prepared.
The
protected trees prove
a challenge
And
once in the ground, the piles
need to be tested for their load
bearing capabilities
The
steel piles protrude from
the earth
The
Cellcore goes into the trench
and is covered with blinding
A
Cross section showing how
Cellcore creates the void to protect
the ground beam
The
blinded trenches before piles
are cut to length
The
cut piles with the starter bars in position - Pecafil at the ready
Pecafil
in place - 3 men,
1 day - a great result
Reinforcement
bars awaiting
mesh to create reinforced wall
ReBars
connected and now most
of the starter bars in place for
the reinforced wall
The
Pochins lorry prepares
Gives
you an idea of the
reach we needed
As
the photo was described to
me - 'some sad old git playing
with the big boys toys.'
Everything
in this picture - a
clear idea of the days operation
Lower
level - pour complete.
Upper level continues
Utility
and drainage being installed.
Note kicker for reinforced wall.
Shuttering
trays for reinforced
wall being positioned
Soakaway
for the internal pond
Shuttering
the rebar and
mesh visible
Reinforced
wall being poured
Stirling
Lloyd (tanking/waterproofing) undercoating the primed wall
Topcoat
being applied - whole job complete in 6 hours
Blockwork
set out in preparation
for the beam and block flooring
Level
1 beam and block flooring
finished and ready for grouting
Level
2 almost complete and
ready for grout
Level
2 appearing - at last better
weather is with us again
As
a result of the shape of the
window Tony, one of the Blockies,
wanted to know if I had a pet giraffe
Level
1 showing the garage and
utility area - note the blockwork built
off the tanked reinforced wall
The
chaps from Drill-Cut the diamond drilling firm who came to sort out
THE error - 2 missed windows in the
reinforced wall! Don't ask!
Front
elevation of the living area
awaiting steels
Northern
wall of the accommodation
area showing the flying window
Western
accommodation
elevation awaiting steels.
Western
elevation of living area
Level
1 ready to receive
structural steels
Level
2 ready for steels
Fabrication
at L G Kimbers - the
largest column in the paint shop
More
columns in the paint shop
Welding
a column fixing arm
Tidying up a Parallel Flange
Channel for the paint shop
One
of the large horizontal beams
on Level 1 having a cover panel
welded into position
Ainscough
arriving down
our narrow lane
The
first steels being
lifted into position
Chris
the Ainscough driver (mit
cigar) in laid-back mode while
Grand Designs and Kevin McCloud
film in the background
Ray
of Kimbers lifts another large
section of steel from the back
of the truck. The truck's large
lifting arm and the Ainscough crane
worked together to erect some steels
The
result of the Crane and the
lifting
arm working together
Steels
fixed to create the cantilevered
bay window over the rear pond
The complex garage section ready to
receive the precast flooring
Steels in place around the pool
and the first flight of stairs
Hanson's precast flooring being
lifted into position by Ainscough
The red bags are known as Crash
Bags and are designed to
protect a falling man
Some of the floor planks require
straps (the red steel) to hold
them
in position
The
flooring fit was filmed and my
damaged foot was the cause of some
mirth and questioning
One for the anoraks (that's me) -
a Junction point for several steels
and difference in the thickness of
the floor plank from 150mm to
100mm - can you spot it all?
With planks in position grout
is lifted to fill the gaps
Another grout delivery
Grout is swept into the gaps which
further strengthens the structure
Level 1 complete except for some
ungrouted planks to facilitate a
further fitting of steel columns
Level
2 all done
Levels 1 & 2 - the whole
job complete in a day
The Hanson guys
-
Paul Pettifor, Dave Worton,
Chris Waller,
Matt Wherly
and Darren Harrison
Students from the Oxford School
of Architecture visiting Cloud 8
The
Kimber rig on the limit
fitting the final column
Level 3 - this gives you the
idea of progress
The
Gilbert protectors do their bit
as the building goes skywards
Main
bedroom - wonderful
airy rooms will be created
Main bedroom with adjoining
bathroom and dressing room
Stairs rebar and formworks between
level 4 and 3 with the large landing
Same stairs after the pour
Poured
stairs level 2-3
The trial wingform roof section
900mm wide
Three sections will be bolted
together and craned into position